Local

The 400 Square Foot Line

Libertyville regulates stormwater on projects far smaller than the county does. Cross a fixed amount of new hard surface and a patio or wider drive picks up an engineer, a storage system and a covenant on your deed.

Most people expect big projects to trigger big rules. A new house, an addition, a subdivision. What they do not expect is that a back terrace of twenty feet by twenty can put a Libertyville homeowner into the same family of regulation, complete with a licensed engineer's drawings. It happens because of a local rule called Appendix P, and it is the single most useful number to know before sketching any new concrete patio or driveway extension in the village.

This page explains where the line sits, how it is measured, and what changes once you are over it. The Village's documents are the authority; we summarise them.

Where the rule comes from

Lake County's Watershed Development Ordinance governs how development handles runoff across the county. Libertyville has adopted it and is certified to enforce it within the village. On its own, the county ordinance only asks for stormwater storage on sites of half an acre or more.

Libertyville sets its own threshold far lower. It first adopted a local amendment in 2015 and revised it in 2019, citing its experience since then and heavier rainfall. The current version, effective 14 August 2019, drops the storage threshold from half an acre to 400 square feet of net new hard surface.

How the 400 is counted

Three details make this more demanding than it first appears.

It is net, against 2015. New or increased hard surface is measured against the property as it existed on 28 July 2015, the date the original local rules took effect, and that baseline is documented with a plat of survey. So the question is not how big this patio is. It is how much hard surface the lot has gained since mid-2015, this project included.

It covers more than concrete. The definition of development runs to buildings, concrete, asphalt, decking, gravel, crushed rock, natural stone, and paver or brick patios laid in sand or concrete. Choosing ordinary pavers or loose stone instead of concrete does not move you to the other side of the line; the only partial exception is a purpose-built permeable system, covered below.

It is described as a lifetime allowance. A footnote to the Village's storage table says that 400 square feet is a single lifetime credit for each property, effective for proposals submitted from 14 August 2019. Read with the 2015 baseline, the sensible assumption is that a small shed one year and a small patio a few years later are added together, not judged separately. Ask the Engineering Division how your lot's history counts before you finalise a layout.

A word on the exact edge. One passage of the regulation speaks of exceeding 400 square feet, while the storage table, another finding and the Village's web page all start the rule at 400 or greater. Plan as though 400 itself is over the line.

What crossing it brings

Below the line, the Village still expects an engineering permit for a change in hard surface, but the job is otherwise an ordinary build. Over it, the list grows considerably.

Appendix P requirementIn practice
On-site stormwater storageA best management practice the Village approves, such as a rain garden, stone storage bed, cistern or underground vault
Site Improvement PlanPrepared by an Illinois licensed Professional Engineer, with a Project Data Worksheet and Checklist
Drainage statementSet wording on the plans about protecting neighbouring property
Restrictive CovenantSigned by the owner and recorded with the Lake County Recorder of Deeds before the permit can issue
As-built drawingsSealed by a licensed engineer or land surveyor, with surface and storage calculations, before the permit closes
OutletA restrictor at least 2 in. across, normally connected to the public storm sewer

None of that is a reason to abandon a good project. But it changes who is involved, how long approval takes, and what the project costs before any concrete arrives. It also leaves a permanent record: the covenant is recorded against the property, which is exactly the kind of document a title search turns up when you come to sell.

How much storage, from the Village table

For net increases between 400 and 4,999 square feet, the required storage volume comes straight from Table P-1. A selection of its rows:

Net new hard surfaceStorage the table requires
Under 400 sq ftNone
400 to 499 sq ft124 cubic feet
600 to 699 sq ft186 cubic feet
1,000 to 1,099 sq ft310 cubic feet
2,000 to 2,249 sq ft620 cubic feet
5,000 sq ft or moreCalculated, not tabled

Where no storm sewer connection is practical, the Village accepts a rain garden, provided it holds the full required volume above ground and is at least six inches deep, with a planting plan from the design engineer.

The surfaces that count at half

Appendix P gives partial credit for surfaces that let some water through. Porous pavement, permeable pavers and modular grid are counted at half their installed area for the storage calculation, and an open-grid deck is treated the same way if the ground under it stays pervious.

The credit has strings. Permeable systems need a perforated underdrain with an approved outlet, a standard detail on the plans and a maintenance plan, and the homeowner signs an acknowledgment of the upkeep before the permit is issued. Stone beneath a surface can also be counted as storage at a third of its volume, using the right grade of stone and an underdrain.

For a design sitting just above the line, that half-credit can be enough to bring the net figure back under 400. For one well above it, it mostly shrinks the storage rather than removing it.

Two map questions to ask first

Some parts of the village are outside Appendix P entirely. Areas shown on the regulation's Exhibit 1 were built with subdivision-scale stormwater systems sized for the hard surface zoning allows, and the rule does not apply there. Other areas, on Exhibit 2, are Special Drainage Areas with extra requirements around the studied high water level.

Before you design anything close to the threshold, ask the Engineering Division which exhibit, if either, your lot falls on. It takes one email and it can change the whole plan.

Designing with the line in view

The practical approach is to get the numbers early. Pull out your plat of survey, total the hard surface added since mid-2015, and hold the new layout against 400. If you land a little over, a tighter outline, a planting bed in place of a corner, or a narrower connecting path can bring it back. If you are well over and still want the space, plan for the engineer from the start rather than discovering the requirement at the permit counter.

We pour the slab; the stormwater design belongs to a licensed engineer. When you have a layout you are happy with, bring the square footage to the people who quote your patio or terrace, and for the recurring side of the same decision, see what extra paving does to the utility bill.

Sources

  1. Village of Libertyville, Appendix P - Stormwater Management Regulations (effective 14 August 2019), with Table P-1, the Project Data Worksheet and Checklist, and Exhibits 1 and 2 - the 400 square foot threshold, the 2015 baseline, the lifetime credit footnote, storage volumes, engineering, covenant and as-built requirements, and the half credit for permeable surfaces. Read 24 September 2026.
  2. Village of Libertyville, Engineering permit documents - Watershed Development Permit triggers and the Appendix P examples of patios, walks and driveway expansions. Read 24 September 2026.

Request a Quote

Get your free, on-site quote.

Tell us about your project and we'll call you back the same day to set up a free measure and price.

Get your free quote

Tell us about your project and we will call you back the same day. No obligation.

What are you looking to do?
Roughly how big?
When are you thinking?

Pricing it out is fine. We will not chase you.

What is your ZIP code?

So we can confirm you are in the service area.

Where should we send it?

Free, no-pressure quote · Serving Lake County, IL

By submitting, you agree to our Privacy Policy and Terms, and consent to be contacted by phone, text, or email about your project, including by automated means. Consent isn't a condition of purchase. Msg & data rates may apply.

Call (262) 228-5293 Text us