Cost
What Concrete Footings Cost, and What Sets the Price
Most of what we pour sits on the surface. Footings are the exception: they go down past the depth the ground freezes, and that one fact sets most of their price. The published ranges, what they assume, and how the Village's own spec changes them.
A driveway, a patio or a walk is a slab that rests on prepared ground. If the ground lifts a little in February, the slab lifts with it and settles back in April. That is fine for flatwork, which is why flatwork is not dug to frost depth. A deck post, a pergola, a porch roof or a garage wall is different. It carries a structure, and a structure that rises and falls with the frost racks, cracks and pulls away from the house. So it stands on footings that start below the ground that freezes.
That makes footings the one kind of concrete on a residential lot where depth, not area, drives the bill. The rest of this page is about what that costs. If the footings are going in alongside a new patio or slab, our concrete patio page describes how the crew sequences both in one visit.
The published figures
HomeGuide's footing cost guide, read on 11 November 2026, gives two kinds of number.
| Job | Published range | Assumptions stated |
|---|---|---|
| Concrete footing, standard project | $700 to $1,500 per footing | Materials and installation, site preparation not included |
| Concrete footing, complex project | $1,500 to $3,000 or more per footing | Sloped sites or specialised footing types |
| Footings poured with a slab | $10 to $14 per sq ft | The combination a garage or addition uses |
The same guide estimates that labour is 40 to 60 percent of a footing job, with contractor time at $50 to $150 an hour, which tells you where the money goes: digging, forming and inspecting, more than concrete.
Read those per-footing figures with care. The guide is written around house foundations, and a footing under a two-storey wall is a much larger thing than the pad under one deck post. We did not find a published per-pier figure for decks or pergolas that we were willing to print, so we are not printing one. What follows explains how to read a pier quote instead.
Footings for a deck, porch or pergola?
Send the post layout or a sketch, and a local crew will price the piers and any slab together, free and on site.
The depth is set locally, and it is not shallow
HomeGuide notes that footings in cold climates often go 3 to 4 feet or more. Libertyville's own number sits in that band. The Village builds foundations to 42 inches below grade, and its deck handout asks for poured piers of at least 8 inches diameter taken down to that same 42 inches. Our page on the piers the Village asks for under a deck covers that handout in detail.
Three and a half feet is a long way down for an 8 inch hole. Every pier is dug, often by an auger, checked for depth before any concrete arrives, and possibly looked at by an inspector before it is filled. In heavy clay the sides of the hole can slump or fill with water between digging and pouring. All of that is time, and time is the larger part of the bill.
What moves a footing quote
How many, not how big. Ten small piers cost more to dig, form and inspect than their volume of concrete suggests, because each one is its own setup. A tidier post layout with fewer, well placed posts can cut the count.
How you get there. A machine auger in an open back yard is quick. Piers dug by hand beside a house, under an existing roof line or behind a fence take far longer.
What comes out of the ground. Spoil from forty-odd inches down has to go somewhere. On a finished lawn that can mean hauling it away rather than spreading it.
What is already down there. Old footings, roots, buried lines and rubble from the original build all slow the auger. Every dig in Illinois starts with a locate request, and the markings sometimes move a pier.
Footing type. HomeGuide's own table lists a spread footing, a pad under each post, as the usual answer for decks and columns, and describes the cheaper thickened-edge slab as unsuitable for cold climates. Around here the thickened-edge shortcut is not one to accept for anything that carries a structure.
The jobs that need footings
| Project | What usually gets poured |
|---|---|
| Deck | A pier under each post, to the Village's depth and diameter |
| Pergola or pavilion | A pier or pad under each post; posts are often anchored to the top |
| Roofed porch or landing | Piers or a foundation wall, depending on size |
| Detached garage or shed with walls | A perimeter footing and a floor slab, priced together |
| Sunroom or addition | Foundation footings and walls, then the slab |
The Village code even contains an exception for the smallest case: a roofed porch or landing of no more than 30 square feet, and no more than 6 feet in any direction, may sit on piers below the frost line rather than a full foundation. Larger porches need more. That is the kind of line worth knowing before a design is drawn, because it can decide what the concrete costs.
Permits and inspection
Footings carry a structure, so they belong to a permitted project rather than standing alone. In Libertyville the building permit fee is calculated from the cost of construction; the formula and the inspection fees are set out in our breakdown of Libertyville's permit fees. Ask at the permit stage whether the Village wants to see the holes open before any concrete goes in. Where it does, the pour date depends on the inspector's calendar as well as the weather.
What we pour and what we do not
The crew digs and pours the footings, piers and any slab. They do not frame the deck, raise the pergola or build the addition. In practice that is a strength rather than a limit: footings go in first, cure, get inspected and then wait for the carpenter, so having the concrete done as its own scheduled step usually suits the builder too. Bring the post layout, the permit drawing if you have one, and the name of whoever is building on top, and the quote can be matched to their plan.
Reading a pier quote without a published per-pier price
Because the published figures describe house foundations, the most useful thing you can do with a deck or pergola quote is make sure it is complete rather than measure it against a national number. A clear quote for footings should tell you:
- How many piers or pads, where, and at what diameter and depth.
- How each hole will be dug, and what happens to the soil that comes out.
- Whether any post anchors or brackets are set in the concrete, and who supplies them.
- Who books the inspection, and what happens to the schedule if it slips.
- Whether a slab, a landing or steps are being poured the same day.
Two quotes that answer all five can be compared fairly. A quote that answers none of them is a number, not a plan. And because the footing locations must match the structure, ask your builder to mark the post positions on the drawing before the concrete is priced. A pier poured a foot from where the post needs to be is one of the more expensive small mistakes in residential building.
Sources
- HomeGuide, Concrete Footing Cost - per-footing ranges, footing and slab per square foot, labour share and hourly rates, cold-climate depth and footing types. Page dated November 24, 2025; figures read 11 November 2026.
- Village of Libertyville, Construction Codes - Municipal Code Chapter 6, the 2018 residential code as amended: foundations 42 in. below grade and the small roofed porch exception (Sec. 6-130). Read September 2026.