Cost
What the Building Permit Adds to a Concrete Job
The Village fee for a new patio or a replaced drive is small next to the pour, and it is worked out by a formula anyone can follow. What it can grow into is the part that deserves the attention.
Most people meet the permit fee as one short line near the bottom of a concrete proposal, and most never ask how it was reached. In Libertyville it is not a flat charge and not a guess by the contractor. The Building Division publishes its method, and the method is simple enough to check against your own quote in a minute or two.
This page sets that method out, adds the inspection and penalty items that sit around it, and then does a little arithmetic of our own so the scale is clear. It does not price the concrete. For the slab itself, including what drives the number up or down, see our concrete patio page, which is where a quote from the crew starts.
The formula the Village publishes
According to the fee summary, building fees follow the cost of construction. Specifically, the Village takes an average estimated cost of all labor and materials, based on the type of construction and the area involved, and multiplies it. Two multipliers matter to a homeowner.
| Fee on the Building Division summary | How it is set | Floor |
|---|---|---|
| Project permit | Construction cost x 0.013 | $65 per discipline |
| Plan review, where plans are reviewed | Construction cost x 0.0012 | $65 |
| Second plan review | No charge | - |
| Third plan review and each after | Half the original review fee | - |
| Renewal or cancellation | 20 percent of the original fee | - |
Note the wording on construction cost. It is the Village's estimate, drawn from published averages, rather than whatever figure appears on your contract. A very keen price does not necessarily shrink the fee, and a generous one does not necessarily swell it. If you want to know the valuation they will use, the Building Division is the office that can say.
Our arithmetic on those multipliers
What follows is our own working from the published rates, not a Village figure and not a job price. It simply turns the decimals into something easier to picture.
| Worked from the published rate (our arithmetic) | Result |
|---|---|
| Permit fee for every $1,000 of assessed construction cost | $13.00 |
| Plan review for every $1,000, where it applies | $1.20 |
| Assessed cost below which the $65 permit minimum governs | $5,000 |
Put plainly, the permit itself is about 1.3 percent of what the Village reckons the work is worth, and small jobs pay the floor. That is modest. Nobody should resize a patio over it, and nobody should be surprised by it either.
What the Village asks for with the application
For a patio or a driveway, the residential permit page asks for broadly the same bundle: a Plat of Survey with the work area highlighted, new dimensions drawn on it if the footprint changes, and two calculations, the impervious surface and the lot coverage both before and after. A Construction Permit Application goes with it. An Engineering Permit Application joins it when the size or shape changes, and for a drive, whenever work reaches into the right-of-way.
Those two calculations are not a formality. They are how the Village checks that the new slab fits the zoning limit for your lot, and they are the step most likely to send an application back. Getting them right the first time saves a second review cycle, even though a second review is free.
Inspections: two included, then a charge
The schedule treats inspections generously at first. The first and second for each discipline cost nothing. From the third onward each visit is $130, and a visit where the work turns out not to be ready is also $130.
Hardscape has its own line. Under special inspections, the summary lists patios as the example and prices that inspection at $65. Whether it applies to your job is a question for the counter, but it is worth knowing the category exists, because a contractor unfamiliar with the Village may not have allowed for it.
The practical lesson is about readiness rather than money. A crew that calls for an inspection before the forms are set and checked risks a wasted trip, a charge, and a day lost waiting for the next slot. Ask how they handle the call.
Where the small fee becomes a larger one
The genuinely expensive lines on the schedule are all consequences, not the permit itself.
| Situation on the fee summary | Published charge |
|---|---|
| Work started without a permit | Project permit fee doubled, $130 minimum |
| Inspection asked for with no active permit | $130 |
| Stop work order, before the placard is removed | $250 |
| Cash bond, where required | $500 to $5,000 |
| Bond administration and inspection | $65 |
None of these arrive if the paperwork is filed before the excavator does. The doubling rule in particular means the cheapest moment to apply is always the start. After a stop work order the fee is the smaller problem; the half-dug site waiting on a decision is the bigger one.
The fees this page does not cover
The Building Division summary is explicit that other departments charge their own permit fees, set out on their own pages or in the Annual Fee Ordinance. For concrete, that mainly means the Engineering Permit that comes with a change in hard surface or any work at the street. We have not quoted those amounts here, and we would rather leave a gap than guess. The engineering side also carries its own cash deposit for right-of-way work, covered separately in our note on getting that deposit returned.
Reading the permit line on a quote
Three questions settle it quickly.
- Is the fee a separate line? It should be. Folded into the concrete price, it cannot be checked.
- Who is applying? Usually the contractor, since the application names the contractors on the job. Confirm it, and ask for a copy of the issued permit before work starts.
- Are the survey and coverage figures included? If you have no current Plat of Survey, finding one is the homeowner's task, and it is the item most likely to delay a start date.
A contractor who can answer all three without hesitation has done this in the Village before. That is worth more than the fee. When you want the slab itself priced, bring your survey to the patio estimate and we will pass it to the crew with your request.
Sources
- Village of Libertyville, Building Division Fee Summary - the construction-cost basis and the 0.013 and 0.0012 multipliers, the $65 minimums, review, renewal, inspection, hardscape, no-permit, stop work and bond charges, and the pointer to the Annual Fee Ordinance for other departments. Read 28 September 2026.
- Village of Libertyville, Residential Permit - the patio and driveway submittal lists, including the survey, the impervious surface and lot coverage calculations, and when an Engineering Permit Application is added. Read 28 September 2026.